Port Clements’ new sewage lagoon is in use, with the remaining work scheduled for completion in 2027, according to the village’s Nov. 16 operations report.

The fence around the lagoon is complete, and a floating cover still needs to be installed. Village staff said the treated wastewater discharged from the lagoon met the village’s permit requirements in October.

The village is also studying whether sewer service could be extended to southern Bayview. Staff said preliminary work is underway and expect the feasibility study to be finished in 2027.