CityWest and Mascon are using backup connections to keep customers online after a Nov. 1 break in the subsea fibre cable that links Haida Gwaii to the mainland. The damage comes as GwaiiTel is asking Daajing Giids for another letter of support to help move a second subsea cable project forward.
In its Nov. 12 update, CityWest said customers in Tlell, Skidegate, Masset and Daajing Giids were getting much slower speeds because the backup link could carry only a fraction of the usual traffic. CityWest warned that streaming, video calls and large downloads could be affected, especially in the evening. TELUS told Haida Gwaii News on Nov. 17 that Mascon customers were still using a backup connection and that speeds could vary depending on the customer’s plan and overall network use. Mascon TV service was unaffected, TELUS said.
CityWest said the damaged section lies in shallow water over a reef close to shore. A Haida Gwaii marine crew is planning the repair, which requires calm seas and suitable tides. CityWest expects the work to take several days once the crew gets on the water. Neither provider gave a restoration date. CityWest said its next update would come by Nov. 19.
CityWest says it will give affected customers a full credit for all their CityWest services for the duration of the disruption, including internet, TV and phone. The credit will be applied automatically once service is restored. TELUS did not say whether Mascon customers would receive a credit.
The damaged cable is part of Connected Coast, a joint project of CityWest and the Strathcona Regional District. Crews began laying the 87-kilometre cable from Tlell toward Bonilla Island in June 2022, and Connected Coast reported the route between Haida Gwaii and Prince Rupert was active by December 2023. In January 2024, CityWest reported four breaks along the Tlell-to-Bonilla Island stretch since Christmas Eve 2023.
The subsea cable comes ashore in Tlell and connects to the island fibre network. GwaiiTel completed the buried line between Old Massett and Skidegate in fall 2016. At the time, a microwave radio link between Old Massett and Mount Hays near Prince Rupert carried traffic across the strait. Today, both Mascon and CityWest use GwaiiTel’s island fibre network to serve homes and businesses.
In March, the province announced up to $24 million through Northern Development Initiative Trust for GwaiiTel’s second subsea cable and said construction would begin that spring. The second cable would give the islands another fibre route to the mainland if the existing line were damaged. In a Nov. 11 email to the village, GwaiiTel said it was still waiting to move ahead and asked for another letter of support to pass along to the funding agency. The request was on council’s Nov. 16 agenda. The email gave no reason for the hold or a revised construction date.
GwaiiTel’s 2024–25 annual report says its original application included a satellite backup alongside the proposed second subsea cable. The society said repeated breaks in the existing Hecate Strait cable had already prompted some households and businesses to sign up for Starlink, either as a backup or as their main internet service. It remains unclear whether the satellite backup is still part of the funded project.